DOMBUD as the General Contractor will carry out for GKN Driveline Polska Sp. z o.o. in the “design build” system in the second stage of the expansion of the plant at ul. Krzywoustego in Oleśnica.

Investor’s data: GKN Driveline Polska Sp. z o.o.
Place of execution: Oleśnica
The area of the extended facility: 18,000 m2.
Area of newly implemented roads and squares: 14,500 m2
Deadline for implementation: October 2018 – September 2019

October 2018 – takeover of the construction site

November 2018

December 2018

January 2019

February 2019

March 2019

April 2019

May 2019

June 2019

July 2019

Copyright © DOMBUD 2017-19